Installation of EVA Vacuum Glass Laminating Machine :
⒈Vacuum Glass Laminating Machine Install control box:
⑴the control box must be carried by 2 people,use 4 nuts to fix it in the specified location.
Attention:Vacuum pump is different from blower.
⑵Electric Control box connection:connect according the signs at wire connecting
① and wire connecting②
+Wire connecting①
+Wire connecting②
+Power connecting
⒉Vacuum Glass Laminating Machine Vacuum pump installation:connect one side of above ¢9mX18m vacuum pipe to the vacuum pipe faucet on the table, another side is connected to the vacuum pump air pump faucet (as picture below)
⒊Vacuum Glass Laminating Machine Orbit installation: adjust the two orbits’ height, make it balance to the inside orbit of the machine, then put the up down car onto the orbit, adjust the width of the orbit; weld the outside orbit and inside orbit connecting to make it fixedness. Fix the outside orbit to the floor with screw (as picture below)
All rights reserved by ★Silicone Vacuuming Bag /Sheet for EVA Glass Laminating Machine / Solar EVA Photovoltaic Panel Encapsulations([email protected] / www.ucolin.com /[email protected])
4.Vacuum Glass Laminating Machine Lift installation: waggle the lift toward the “hour hand” direction, lift going up, waggle the lift backward “hour hand” direction, lift going down.
+Vacuum Glass Laminating Machine Machine carry: as picture below
All rights reserved by ★Silicone Vacuuming Bag /Sheet for EVA Glass Laminating Machine / Solar EVA Photovoltaic Panel Encapsulations([email protected] / www.ucolin.com /[email protected])